Key Details
  • Description This CMU is formed of a battery bank and PCS capable of providing 10MW of power with 23.9MWh of usable energy storage (2 hour duration). The system is connected via switch gear and a transformer to the 132kV network in WPD's South West region.
  • Auction 2023-24 (T-1) One Year Ahead Capacity Auction
  • Delivery Year 2023
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 2.34
  • Connection Capacity (CMU Registry) 9.92 MW
  • Anticipated Capacity (CMU Registry) 2.36 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name ECOTRICITY (SMART GRID) LIMITED
  • Parent Company (CMU Registry) ECOTRICITY GROUP LTD
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4401453790163

Field Value
_id 537035
Type T-1
rank 0.0573088
CMU ID ALBESS
Auction Name 2023-24 (T-1) One Year Ahead Capacity Auction
Component ID 2h10MW
Delivery Year 2023
De-Rated Capacity 3.671
OS Grid Reference ST 649 846
Location and Post Code Old Gloucester Road, Alveston, Bristol, UK, BS35 3TD
Connection / DSR Capacity 9.916
Primary Fuel of Component (empty)
Generating Technology Class Storage (Duration 2h)
Description of CMU Components This CMU is formed of a battery bank and PCS capable of providing 10MW of power with 23.9MWh of usable energy storage (2 hour duration). The system is connected via switch gear and a transformer to the 132kV network in WPD's South West region.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 13390
Type T-4
CMU ID ALBESS
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2026-27 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Alveston 10MW Battery Storage
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2026
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company ECOTRICITY GROUP LTD
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 2.343
Name of Applicant ECOTRICITY (SMART GRID) LIMITED
Primary Fuel Type Storage - Battery
Registered Holder ECOTRICITY (SMART GRID) LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 9.916
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2026-ALBESS-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 2.363
Term of the Capacity Agreement 12
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2023-03-31
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 2.343
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4401453790163
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 12
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2026/2027, 2027/2028, 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2024-05-19
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved 2024-05-14
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 12