Search Map View Statistics Support Us Help Login Register
Marchwood ERF, Oceanic Way, Marchwood Industrial Park, Normandy Way, Marchwood, Hampshire SO40 4BD Map

General Information

Key Details
  • Description Municipal waste incineration plant located in Marchwood Hampshire. It is based on boilers supplying steam to a turbine-generator.
  • Auction 2022-23 (T-3) Three Year Ahead Capacity Auction
  • Delivery Year 2022
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 10.37
  • Connection Capacity (CMU Registry) 12.08 MW
  • Anticipated Capacity (CMU Registry) 10.37 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name VEOLIA UK LIMITED
  • Parent Company (CMU Registry) VEOLIA ENVIRONNEMENT SA
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4402078125000

Field Value
_id 150059
Type T-3
rank 0.0706241
CMU ID MAERF5
Auction Name 2022-23 (T-3) Three Year Ahead Capacity Auction
Component ID MAERF5
Delivery Year 2022
De-Rated Capacity (empty)
OS Grid Reference SU 396 112
Location and Post Code Marchwood ERF, Oceanic Way, Marchwood Industrial Park, Normandy Way, Marchwood, Hampshire SO40 4BD
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class Energy from Waste
Description of CMU Components Municipal waste incineration plant located in Marchwood Hampshire. It is based on boilers supplying steam to a turbine-generator.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 10027
Type T-4
CMU ID MAERF5
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2023-24 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Marchwood ERF
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2023
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company VEOLIA ENVIRONNEMENT SA
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 10.366
Name of Applicant VEOLIA UK LIMITED
Primary Fuel Type Waste
Registered Holder VEOLIA UK LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 12.08
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2023-MAERF5-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 10.366
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2020-04-17
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 10.366
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4402078125000
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2023/2024
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)