Woodhouse Energy Centre A. Pearson and Sons? Nursery Alderley Edge SK9 7UW Map

General Information

Key Details
  • Description The CMU component, CASQ17 supplies heat, CO2 and electricity to the onsite nursery and facilities.
  • Auction 2022-23 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2022
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 2.89
  • Connection Capacity (CMU Registry) 3.21 MW
  • Anticipated Capacity (CMU Registry) 3.04 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name P3P ENERGY MANAGEMENT AE LIMITED
  • Parent Company (CMU Registry) P3P PARTNERS LLP
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4402036676200

Field Value
_id 292086
Type T-4
rank 0.0706241
CMU ID CASQ18
Auction Name 2022-23 (T-4) Four Year Ahead Capacity Auction
Component ID CASQ17
Delivery Year 2022
De-Rated Capacity (empty)
OS Grid Reference SJ 833 774
Location and Post Code Woodhouse Energy Centre A. Pearson and Sons? Nursery Alderley Edge SK9 7UW
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class Combined Heat and Power (CHP)
Description of CMU Components The CMU component, CASQ17 supplies heat, CO2 and electricity to the onsite nursery and facilities.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 5261
Type T-4
CMU ID CASQ17
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2021-22 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Woodhouse Energy Centre
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2021
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company P3P PARTNERS LLP
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 2.894
Name of Applicant P3P ENERGY MANAGEMENT AE LIMITED
Primary Fuel Type Gas
Registered Holder P3P ENERGY MANAGEMENT AE LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 3.215
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2021-CASQ17-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 3.038
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2018-03-20
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 2.894
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4402036676200
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2021/2022
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)