Heatherywood Road, Kirkcaldy, KY1 3NW (2 components)

1hr Duration battery storage project. (2)

Storage (Duration 1h)
2.3 MW
Active - 2027-28 (T-4), 2026-27 (T-4)
BRLR, land east of Redhouse electricity substation, Heatherywood Road, Kirkcaldy, Fife, KY1 3NW. (1 components)

Battery energy storage system (1c rating, NMC lithium ion) comprising eight inverters with nominal power output rating of 2.0MW each (16.0MW total). The connection capacity of the BESS has been …

Storage (Duration 1h)
1.0 MW
Active - 2028-29 (T-4)
Land North of Heatherywood Road, Kirkcaldy, Fife, KY1 3NW (5 components)

New build storage facility (4)

Storage Storage (Duration 1h)
Active - 2024-25 (T-4), 2023-24 (T-4), 2022-23 (T-4) (and 1 more)
Heatherywood Road, Kirkcaldy KY1 3NW (2 components)

1hr duration battery storage project. (2)

Storage (Duration 1h)
Active - 2025-26 (T-4), 2022-23 (T-1)