ScottishPower Energy Retail Limited

7 unique locations (234 components)

Active MW: 71.28 MW
Inactive MW: 4208.18 MW
Netherlands Way, Kiln Lane Industrial Estate, Starlingborough, UK, DN41 8DF (4 components)
• A 20MW New Build Battery Storage Site
• A 40MW New Build Battery Storage Site
Inactive • 2022-23 (T-4)
Kirklees Energy from Waste Plant Vine Street Huddersfield, Yorkshire HD1 6NT (29 components)
• A new build gas fuelled power generating unit comprising multiple reciprocating engines.
• Existing Energy from Waste Plant
• The CMU component at Whitehouse Farm is an energy storage system comprised of Lithium-ion batteries. The system will have a 40 MW export capacity and an import capacity of 40 MW.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
EDF Energy, Torness power station, Torness, Dunbar, East Lothian, EH42 1QU (34 components)
• Torness Power Station CMU 1: [TN1-23] T_TORN-1 + (50% x T_TORN-D)
• Torness Power Station CMU 1: [TN1-24] T_TORN-1 + (50% x T_TORN-D)
• Torness Power Station CMU 2: [TN2-24] T_TORN-2 + (50% x T_TORN-D)
Active • 2028-29 (T-4), 2027-28 (T-4) ...
EDF Energy, Hunterston B power station, West Kilbride, Ayrshire, KA23 9QX (40 components)
• Hunterston B Power Station CMU 7: [HU7-21] T_HUNB-7 + (50% x T_HUNB-D) + (50% x E_HUNB-11S)
• Hunterston B Power Station CMU 8: [HU8-20] T_HUNB-8 + (50% x T_HUNB-D) + (50% x E_HUNB-11S)
• Hunterston B Power Station CMU 8: [HU8-21] T_HUNB-8 + (50% x T_HUNB-D) + (50% x E_HUNB-11S)
Active • 2025-26 (T-4), 2024-25 (T-4) ...
Chichester Food Park, Bognor Rd, Chichester PO20 1NW, United Kingdom (99 components)
• Genset 2. ROCable hydro units within the BMU are not included in the CMU.
• Load Response - Automated Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Centrica Peterborough Power Station, Storeys Bar Road, Peterborough, PE1 5NT. (26 components)
• 1 x hydro turbine & synchronous generator
• 4MW battery co-located with a solar farm
• Centrica Peterborough Power Station (PPS) is an Open Cycle Gas Turbine (OCGT) electricity generating station.
Active • 2024-25 (T-4), 2023-24 (T-4) ...
19 Howard Road, Park Farm Industrial Estate, Redditch, Worcestershire, B98 7SE (2 components)
• Existing OCGT module
• The CMU component at the Ipsley Battery Storage Facility will be an energy storage system comprised of batteries and will have an import capacity of 4000kVa and an export capacity of 4000 kVA.
Inactive • 2023-24 (T-4)
Loading map...
Showing 7 locations