Home Technologies Companies Locations Map Explorer FAQ ChatGPTChatGPT Buy Me A Coffee Help Login Register
Theme
Light Dark Auto
Quick Menu
Loading...
Loading...

SSE Generation Limited

29 unique locations (655 components) - Page 1 of 2

Active MW: 6861.98 MW
Inactive MW: 10342.73 MW
Woodhouse Energy Centre A. Pearson and Sons? Nursery Alderley Edge SK9 7UW (7 components)
• The CMU Component will have a connection capacity of 3.298MW net of 46kW auxiliary load. Gas-fired reciprocating engine will be the technology used.
• The CMU component is installed in the Woodhouse Energy Centre that is located at a Nursery site in Alderley Edge.
• The CMU component, CASQ17 supplies heat, CO2 and electricity to the onsite nursery and facilities.
Active • 2028-29 (T-4), 2023-24 (T-4) ...
Watson Street Power Station, Burtonhead Road, St Helens, WA9 5EA (19 components)
• A gas engine CHP site providing hot water to a local district heating network
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• One CHP engine in a horticultural environment with no auxilliary load.
Active • 2027-28 (T-4), 2025-26 (T-4) ...
Smurfit Kappa SSK, Mount Street, Nechells, Birmingham B7 5RE (15 components)
• 4MW battery co-located with a solar farm
• 8.3MW Gas Turbine installation
• Unit 3 Cruachan pump storage hydro plant
Active • 2024-25 (T-4), 2023-24 (T-4) ...
Sloy Power Station, Arrochar, G83 7DP (26 components)
• 1 x hydro turbine & synchronous generator
• Genset 2
• Genset 3
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Rocks Dryer, Rosvear Road, Bugle, St. Austell, PL26 8PJ (14 components)
• Gas CHP
• Gas CHP in St. Austell
• N/A
Active • 2026-27 (T-4), 2024-25 (T-4) ...
Power Station Road Isle of Grain Rochester ME3 0AR (69 components)
• Grain B CCGT Unit 6 Grain B power station provides heat to the Grain LNG regasification facility.
• OCGT from Grain U1. Fuel is Diesel as specified in BS EN590
• OCGT from Grain U4. Fuel is Diesel as specified in BS EN590
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Pembroke Rd, Merlin's Bridge, Haverfordwest SA61 1JN (11 components)

Existing Generation on existing site - CHP

Active • 2028-29 (T-4), 2027-28 (T-4) ...
Par CHP, Par Docks, Par, St. Austell, PL24 2BN (13 components)
• CHP unit
• Gas CHP located in St. Austell
Active • 2026-27 (T-4), 2025-26 (T-4) ...
Nr 125 Park Lane Cottingham East Yorkshire HU16 5RX (23 components)
• CHP at a horticultural environment.
• CHP at horticultural site
• Gas CHP engines in commercial horticultural environment with no auxilliary load
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Maxi Readymix Concrete, Enderby Road,Industrial Estate, Whetstone, Leicester LE8 6HZ (5 components)
• New build power station comprised of multiple reciprocating engines.
• On-site existing CHP generating unit
Inactive • 2022-23 (T-3), 2021-22 (T-4) ...
Lochay Power Station, Killin, Stirling, FK21 8UA (23 components)
• Genset 1.
• Genset 2.
• Genset 2. ROCable hydro units within the BMU are not included in the CMU.
Active • 2028-29 (T-4), 2026-27 (T-4) ...
Langstone Power Generation Plant, Southmoor Lane, Havant, Hampshire, PO9 1JW (10 components)
• Grain B CCGT Unit 6 CHP element is via supply of heat to Grain LNG regasification facility
• Municipal waste incineration plant located in Chineham Hampshire. It is based on one boiler supplying steam to a turbine-generator.
• New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant
Active • 2026-27 (T-4), 2025-26 (T-4) ...
Keadby Power Station, Keadby, Trentside, Scunthorpe, DN17 3EF (5 components)
• Grain B CCGT Unit 8 CHP element is via supply of heat to Grain LNG regasification facility
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• Single combined cycle gas turbine with supplementary firing
Active • 2024-25 (T-4), 2022-23 (T-3) ...
JDE, Ruscote Avenue, Banbury, Oxfordshire, OX16 2QU (27 components)
• A CCGT station consisting of two Alstom GT26A gas turbines, with an Alstom heat recovery steam generator each that produces steam for one ABB steam turbine and is based near Runcorn in Cheshire. Metering of output is Net of auxillary load.
• Centrax gas turbine CHP
• Centrax gas turbine which will have bespoke metering in installed to capture the generation output.
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Great Western Rd, Gloucestershire, Gloucester GL1 3NN (15 components)
• Aggregate CMU from multiple sources
• BM unit T_DINO-6 at Dinorwig Power Station (Pumped Storage)
• CHP installation in the Energy Centre of an NHS Hospital. The CHP will be sub metered.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Furness Vale Industrial Estate, Station Road, Furness Vale, SK23 7SW (3 components)
• A gas fuelled electrical power generating unit comprising multiple reciprocating engines.
• Energy Centre with gas CHP engines providing district heating and power to local community. All generation unit capacities are nominal and allow for site-specific variations.
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Excel Energy Centre Warehouse R Royal Victoria Dock Northside London E16 1BA (47 components)
• 1.2 MW Combined Heat and Power Engine.
• 1.6 MW Combined Heat and Power Engine
• The proposed power plant would consist of a number new highly efficient gas fired generating units plus ancillary equipment. Each genset is based on advanced reciprocating engine technology.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
EP Langage Power Station, Holland Road, Plymouth, PL7 5AW. (10 components)
• EP Langage Power Station is a Combined Cycle Gas Turbine (CCGT) electricity generating station.
• Load reduction on site supported by non-exporting standby generation.
• One 8 MWe Gas Turbine Cogeneration Unit (GT2)
Active • 2027-28 (T-4), 2026-27 (T-4) ...
Enterprise Drive, Coven, Wolverhampton, Staffordshire WV10 7DY (9 components)
• CHP Plant connected to Private Wire System (operated by INEOS Infrastructure (Grangemouth) Limited) with Connection to NETS
• Municipal waste incineration plant located in Staffordshire. It is based on boilers supplying steam to a turbine-generator.
• Reciprocating genset
Active • 2028-29 (T-4), 2027-28 (T-4) ...
EDF Energy, Hartlepool power station, Tees Road, Hartlepool, TS25 2BZ (57 components)
• Hartlepool Power Station CMU 2: [HR2-23] T_HRTL-2
• Hartlepool Power Station CMU 2: [HR2-24] T_HRTL-2
• Hartlepool Power Station CMU 1: [HR1-24] T_HRTL-1
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Drax Power Station, Selby, North Yorkshire, YO8 8PH (67 components)
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-10G under the BSC.
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-12G under the BSC.
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-9G.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Centro 3, Maxted Close, Hemel Hempstead, Herts, HP2 7SU (6 components)
• DSR Component providing load turn down at a data centre
• Energy Centre with gas CHP engines providing district heating and power to local community. All generation unit capacities are nominal and allow for site-specific variations.
Active • 2025-26 (T-4), 2023-24 (T-4) ...
Carrington Power Station 132 Manchester Road Carrington Manchester M31 4AY United Kingdom (57 components)
• CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network
• The CMU component is a combined cycle gas turbine
• one CHP (1.9MW rating) in a horticulatural environment with no aux load
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Broadgreen Hospital, Thomas Drive, Liverpool L14 3LB (14 components)
• 1 x Gas reciprocating engine with a total rated gross power capacity of 2.000 MW and total net power capacity of 1.949 MW
• 1 x Gas reciprocating engine with a total rated gross power capacity of 2.200 MW and total net power capacity of 2.181 MW
• ElecLink will have a transmission capacity of 1000MW corresponding to its grid connection agreements and link the 400kV AC grids of France and Great Britain. ElecLink will employ high voltage direct current converter stations using voltage source converter technology at each side of the Channel Tunnel. 400kV AC underground cables will connect the converter stations to the TSO's high voltage substations: Sellindge (NGET, UK) and Les Mandarins (RTE, France). The converter station on the Eurotunnel site at Folkestone will be connected by one 400kV AC cable circuit to the National Grid substation at Sellindge. The route length is approximately 14km. The converter station on the Eurotunnel site at Coquelles will be connected by one 400kV AC cable circuit to the RTE substation at Les Madarins. The route length is approximately 3.5km. An approximately 52km long HVDC cable circuit will connect the two converter stations via the Channel Tunnel between Folkestone and Coquelles. This will involve two single-core HVDC cables operating at +-320kV DC. Please note that in the section below we provided an address for the CMU which relates to the UK converter station site. Of course, given the CMU is an interconnector there are a variety of sites which are owned/managed by ElecLink and relate to the CMU, as additional information we have provided details of those sites below. Please note also that we have provided the grid reference points which most closely correspond to the sites, however the postcode for the address will capture a wider area. Sellindge substation Church Lane Aldington Ashford TN25 6SS Grid reference: TR082383 Converter station at Coquelles, France Eurotunnel Entrance Centre De Secours, 3573 Chemin Rouge Cambre, 62231 Coquelles, France Grid reference: TR657202 We wish to clarify here that while ElecLink has acceded to the BSC we have not yet begun installing or testing metering systems. Therefore, MPANs and BMU IDs do not apply to the ElecLink CMU at this point in time. ElecLink will ensure that the Delivery Body is updated as required once the metering systems are completed.
Active • 2025-26 (T-4), 2025-26 (T-1) ...
Loading map...
Showing 25 locations