RWE GENERATION UK PLC

11 unique locations (410 components)

Active MW: 14629.16 MW
Inactive MW: 48084.56 MW
EDF Energy, Heysham 2 power station, Morecambe, Lancashire, LA3 2XH (43 components)
• Heysham 2 Power Station CMU 7: [HY2723] T_HEYM27 + (50% x T_HEYM2-D)
• Heysham 2 Power Station CMU 7: [HY2724] T_HEYM27 + (50% x T_HEYM2-D)
• Heysham 2 Power Station CMU 8: [HY2824] T_HEYM28 + (50% x T_HEYM2-D)
Active • 2028-29 (T-4), 2027-28 (T-4) ...
EDF Energy, Torness power station, Torness, Dunbar, East Lothian, EH42 1QU (34 components)
• Torness Power Station CMU 1: [TN1-23] T_TORN-1 + (50% x T_TORN-D)
• Torness Power Station CMU 1: [TN1-24] T_TORN-1 + (50% x T_TORN-D)
• Torness Power Station CMU 2: [TN2-24] T_TORN-2 + (50% x T_TORN-D)
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Ferrybridge Power Station, Stranglands Lane, Knottingley, West Yorkshire, WF11 8SQ (125 components)
• Aux. load separately metered
• Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 5MW
• GT8
Active • 2026-27 (T-4), 2025-26 (T-4) ...
Ffestiniog Power Station, Tanygrisiau, Blaenau Ffestiniog, LL41 3TP (48 components)
• 1hr duration battery storage project.
• Load Response - Automated Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2027-28 (T-4), 2026-27 (T-4) ...
Land off Sundridge Hill, Cuxton, Rochester, ME2 1LB. (13 components)
• A gas fuelled electrical power generating unit comprising multiple reciprocating engines.
• The CMU component at Cuxton is an energy storage system comprised of batteries with an import and export capacity of 49.5MVA.
• The CMU component at Cuxton is an energy storage system comprised of batteries with an import and export capacity of 49.5MW. Battery capacity will be reduced to 38.5MWh after 15 years of operation.
Active • 2026-27 (T-4), 2024-25 (T-1) ...
Little Barford Power Station Little Barford St Neots PE19 6YT (32 components)
• 49.9MW Lithium Ion Batteries and power conversion system installed in a compound at Chickerell Substation.
• Little Barford 1 CCGT MSID: 4052
• Little Barford 1 OCGT . fuel type is distillate MSID: 4052
Active • 2028-29 (T-4), 2026-27 (T-4) ...
Pembroke Power Station Pembroke Dyfed SA71 5SS (55 components)
• Pembroke 21 - CCGT MSID: 7237
• Pembroke 41 - CCGT MSID: 7237
• Pembroke 51 - CCGT MSID: 7237
Active • 2028-29 (T-4), 2027-28 (T-4) ...
South Cornelly Trading Estate, Porthcawl Road, Bridgend, CF33 4RE (23 components)
• 49.900MW/49.900MWh battery storage asset, 1 hour duration
• Gas fired CHP unit
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
Active • 2028-29 (T-4), 2025-26 (T-4) ...
Units 1-4, 730 London Road, West Thurrock, Essex, RM20 3NL (8 components)
• 20MW power plant comprising reciprocating engines. The power plant will be connected to the local distribution network and local gas network.
• DSR components to be assigned prior to the start of the Delivery Year.
• The CMU component at Tollgate Farm is an energy storage system comprised of batteries with an import and export capacity of 49.5MW.
Active • 2025-26 (T-4), 2023-24 (T-4) ...
WEMBLEY ENERGY CENTRE, HARBUTT ROAD, OFF ENGINEERS WAY, WEMBLEY, LONDON, HA9 0NH (8 components)
• A gas engine CHP site providing hot water to a local district heating network
• Didcot B5 - CCGT MSID: 4055
• one CHP (1.9MW rating) in a horticulatural environment with no aux load
Active • 2026-27 (T-4), 2025-26 (T-4) ...
Wolverhampton Power, Northern Steel Rocks, Cross Street, Wolverhampton, WV1 2HS (21 components)
• 16 MW power plant comprising 8 x 2MW gas reciprocating engines. The power plant is connected to the local distribution network and local gas network.
• 16MW Power plant comprising reciprocating engines. The Power plant is connected to the local distribution and gas network.
• CMU consisting of multiple gas reciprocating engines and alternators
Active • 2028-29 (T-4), 2024-25 (T-4) ...
Loading map...
Showing 11 locations