GRIDBEYOND LIMITED

8 unique locations (83 components)

Active MW: 804.46 MW
Inactive MW: 304.02 MW
Trow Green Farm, Trow Green, St Brevials, GL15 6QP (4 components)

The CMU component at Trow Green Farm is an energy storage system comprised of Lithium-ion batteries. The system will have a 10 MW export capacity and an import capacity of …

Inactive • 2023-24 (T-4), 2022-23 (T-3) ...
Thrybergh Weir Kilnhurst Mexborough South Yorkshire S64 5TJ (13 components)
• 1.200 MW of demand reduction
• 1.200MW Battery Energy Storage System
• The CMU component at Thrybergh is an energy storage system comprised of Lithium-ion batteries. The system will have a 1.2 MW export capacity and an import capacity of 1.2 MW
Active • 2024-25 (T-4), 2022-23 (T-4) ...
Plot E, XL Business Park, Corner Statham Road and Spa Lane, Skelmersdale, Lancashire, United Kingdom, L40 6JQ (14 components)
• A New Build battery energy storage system.
• An existing battery energy storage system.
• The New Build CMU, will consist of the design, procurement of new Apparatus, build and operation of a battery energy storage system, consisting of power conversion units(inverters), battery cells, transformer, cabling and other equipment as necessary for the operation of an energy storage system. It will be connected to the distribution network.
Active • 2026-27 (T-4), 2025-26 (T-1) ...
Old Gloucester Rd, Alveston, Bristol, UK, BS37 9TU (8 components)

This CMU is formed of a battery bank and PCS capable of providing 10MW of power. The system is connected via switch gear and a transformer to the 132kV network …

Inactive • 2022-23 (T-4), 2021-22 (T-4) ...
Land North East of Jamesfield Organic Centre, Newburgh, KY14 6EW (6 components)
• A new build 29MW battery energy storage system
• A new build 30MW battery energy storage system
Active • 2025-26 (T-4), 2024-25 (T-4) ...
Land adjacent to Vauxhall Effluent Treatment Works, North Road, Ellesmere Port, Cheshire CH65 1AL (14 components)

The CMU will be formed of multiple individual storage units controlled centrally and exporting to the distribution system.

Inactive • 2020-21 (T-4), 2019-20 (T-1) ...
Brotherton Weir, Knottingley West Yorkshire WF11 8HR (11 components)
• 1.2 MW of demand reduction
• 1.200MW Battery Energy Storage System
• The CMU component at Knottingley is an energy storage system comprised of Lithium-ion batteries. The system will have a 1.2 MW export capacity and an import capacity of 1.2MW
Active • 2024-25 (T-4), 2022-23 (T-4) ...
Loading map...