CENTRICA BUSINESS SOLUTIONS UK OPTIMISATION LIMITED

8 unique locations (297 components)

Active MW: 588.77 MW
Inactive MW: 4445.47 MW
Chichester Food Park, Bognor Rd, Chichester PO20 1NW, United Kingdom (73 components)

Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.

Active • 2028-29 (T-4), 2027-28 (T-4) ...
Fasnakyle Power Station, Cannich, Beauly, IV4 7NB (29 components)
• Generating Unit 1
• Generating Unit 2
• Generating unit 3.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Lawford Rd, Rugby CV21 2RY, United Kingdom (22 components)

Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.

Active • 2028-29 (T-4), 2027-28 (T-4) ...
New Galloway, Castle Douglas, Kirkcudbrightshire, DG7 3SF, Scotland (39 components)
• Glenlee hydro power station - Unit 1, part of the Galloway hydroelectric scheme. The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
• Glenlee hydro power station - Unit 1, part of the Galloway hydroelectric scheme. The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
• Glenlee hydro power station - Unit 2, part of the Galloway hydroelectric scheme The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
SIMEC Lochaber Power Lochaber Smelter North Road Fort William PH336TH (54 components)
• Hydro power turbine generator Unit 1 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 3 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 5 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
South Cornelly Trading Estate, Porthcawl Road, Bridgend, CF33 4RE (16 components)
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
• The CMU will be formed of multiple individual generating units controlled centrally and exporting to the distribution system.
Active • 2028-29 (T-4), 2025-26 (T-4) ...
Staythorpe Power Station Staythorpe Newark Nottinghamshire NG23 5PS (46 components)
• Staythorpe 1 - CCGT MSID: 7210
• Staythorpe 2 - CCGT MSID: 7210
• Staythorpe 4 - CCGT MSID: 7210