BALANCE POWER PROJECTS LIMITED

16 unique locations (486 components)

Active MW: 198.93 MW
Inactive MW: 421.41 MW
Wissington Sugar Factory British Sugar plc College Road Wissington King's Lynn PE33 9QG (33 components)
• A gas fuelled electrical power generating unit comprising multiple reciprocating engines.
• Existing CCGT
• The CMU is a gas fired CCGT CHP
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Trumfleet Generation Site, Marsh Lane, Trumfleet, Doncaster. DN6 0DU (23 components)
• A new open cycle power station comprising gas turbine(s) and associated balance of plant. This will be constructed on brownfield land in Stanford-Le-Hope, Essex. Metering of output is Net of auxillary load.
• The CMU will be formed of multiple individual diesel reciprocating generating units controlled centrally and exporting to the distribution system.
• The CMU will be formed of multiple individual generating units controlled centrally and exporting to the distribution system.
Active • 2024-25 (T-4), 2023-24 (T-4) ...
South Cornelly Trading Estate, Porthcawl Road, Bridgend, CF33 4RE (23 components)
• 49.900MW/49.900MWh battery storage asset, 1 hour duration
• Gas fired CHP unit
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
Active • 2028-29 (T-4), 2025-26 (T-4) ...
Selby Energy Limited, Selby Road, Northpoint Business Park, Eggborough, North Yorkshire. DN14 0JT (2 components)
• A gas fuelled electrical power generating unit comprising multiple reciprocating engines.
• One of three CHP units at Energy Center, Ashton Street, Liverpool, L69 3GB
Inactive • 2022-23 (T-4), 2022-23 (T-3)
Ribblesdale Cement Works, West Bradford Road, Clitheroe, BB7 4QF (19 components)
• Combined Heat and Power Plant Stratford made up of 2 generators totalling 6.6MW however the generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.838 MW as per the 3 highest export peaks
• Hanson 2 - DSR Turn Down/ Load Reduction
• Storage facility
Active • 2024-25 (T-1), 2023-24 (T-4) ...
Ninewells Hospital, Dundee, DD2 1UB (10 components)
• A Packaged 3.976MW, 11kV CHP
• A Packaged 3.976MW, 11kV natural gas fired reciprocating engine CHP
Inactive • 2022-23 (T-3), 2021-22 (T-4) ...
Mersey Wharf Business Park, Dock Road South, Bromborough Pool, Wirral, Merseyside, CH62 4SU (20 components)
• 16 MW power plant comprising gas reciprocating engines. The power plant is connected to the local distribution network and local gas network.
• 16MW Power plant comprising reciprocating engines. The Power plant is connected to the local distribution and gas network.
• Ratcliffe Unit 3 coal-fired unit
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Maple Quay CHP, Montreal House, Surrey Quay Road, Rotherhithe, London, SE16 7AP (16 components)
• 2 x 2.5 MW gas fuelled generators installed on land east of Griffiths Road.
• A gas engine CHP site providing hot water to a local district heating network
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2028-29 (T-4), 2026-27 (T-4) ...
Located on the land of Westlands Farm, Westlands Lane, Whitley, Melksham, SN12 7QG. (12 components)
• A gas engine CHP site providing hot water to a local district heating network
• Battery Storage Plant
• Flour & semolina milling business
Active • 2025-26 (T-4), 2024-25 (T-1) ...
Liberty Lochaber Smelter, Fort William, Scotland PH33 6TH (53 components)
• A gas fuelled electrical power generating unit comprising multiple reciprocating engines.
• CHP engine in a horticultural environment, natural gas, no aux load
• Existing CCGT Unit
Active • 2024-25 (T-4), 2023-24 (T-4) ...
Land adjacent to the SW of Glassenbury BESS, Glassenbury Road, Cranbrook, Kent, TN17 2QL (2 components)
• A new build storage station using batteries
• Steam Driven Turbo Alternator 8G4 7MWe (derated to 4 MWe for mechanical reasons)
Inactive • 2023-24 (T-4), 2020-21 (T-4)
Kings Yard Energy Centre, Carpenters Lane, Stratford, London E15 2DU (35 components)
• A Battery Energy Storage System.
• Combined Heat and Power Plant Olympic Park London
• Combined Heat and Power Plant, St Marks Boiler House, capacity of generator 1.600MW. Although the supplier of the settled hh meter has provided their three peaks, we have used the combined peak of all the component units to determine the capacity of LDEC as a single CMU hence the connected capacity above being consistent with the three peaks of the combined units.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Furness Vale Industrial Estate, Station Road, Furness Vale, SK23 7SW (3 components)
• A gas fuelled electrical power generating unit comprising multiple reciprocating engines.
• Energy Centre with gas CHP engines providing district heating and power to local community. All generation unit capacities are nominal and allow for site-specific variations.
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Fiddler's Ferry Power Station, Widnes Road, Cuerdley, Warrington, WA5 2UT (166 components)
• GT3
• Genset 1.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2027-28 (T-4), 2025-26 (T-4) ...
Coldstore 3, Park Road, Holmewood Industrial Park, Chesterfield S42 5UY (12 components)
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• Mixture of load reduction on flexible electricity consuming processes including refrigeration air-conditioning pumping and lighting and standby generation.
• The proposed power plant would consist of a number new highly efficient gas fired generating units plus ancillary equipment. Each genset is based on advanced reciprocating engine technology.
Active • 2025-26 (T-4), 2023-24 (T-4) ...
Aston University, Aston Triangle, Birmingham, West Midlands, B4 7ET (57 components)
• 1MW Combined heat and Power Plant at Aston University. Total Capacity is 3.000MW, consisting of two generators - 2.000MW and 1.000MW
• 2MW Combined heat and Power Plant at Aston University. Total Capacity is 3.000MW, consisting of two generators - 2.000MW and 1.000MW
• Containerised high speed gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 9MW.
Active • 2028-29 (T-4), 2027-28 (T-4) ...