ADD Renewables Limited

91 unique locations (683 components) - Page 1 of 4

Active MW: 12.75 MW
Inactive MW: 53.00 MW
10-14 Birmingham Road, West Bromwich, B71 4LD (5 components)
• Energy Centre comprising of Lean Burn, Acoustically Treated Natural Gas Reciprocating Engines.
• New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant
Inactive • 2022-23 (T-4), 2021-22 (T-1)
Airbus, Chester Road, Broughton, Wales CH4 0DR (4 components)
• "Planet Ice - UK Croft Road, Coventry, CV1 3AZ The CMU Component reduces import demand by turning off equipment and other non-essential loads."
• Gas fired CHP
Inactive • 2017-18 (TR), 2017-18 (T-1)
Asda Redditch, Jinnah Road, Redditch, B98 7ER (11 components)
• CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network
• Load curtailment
Active • 2028-29 (T-4), 2025-26 (T-4) ...
BALL BEVERAGE PACKAGING, MAYNARD ROAD, EAST SEGRO PARK, BURTON LATIMER, KETTERING, NN15 5ZS (1 component)

The CMU Component reduces import demand by turning off equipment and other non-essential loads.

Active • 2025-26 (T-4)
Banbury Power Hennef Way Grimsbury Banbury OX16 3WA (3 components)

Banbury Power will be a 12MW power plant comprising gas reciprocating engines. The export of the power plant is connected to the local distribution network via two separately metered 6MW …

Inactive • 2019-20 (T-1)
Barco battery generating station, Barco, Shindour Feddal Hill Wood, Dunblane, FK15 9RD. Located southeast of the existing Braco West Substation (1 component)

Kiln Power is a 16 MW power plant comprising gas reciprocating engines. The export of the power plant is connected to the local distribution network via two separately metered 8MW …

Active • 2025-26 (T-4)
Baunton WTW, A435, Baunton, Cirencester, United Kingdom, GL7 7BQ (4 components)

The CMU Component reduces import demand by turning off equipment and other non-essential loads.

Active • 2025-26 (T-4), 2024-25 (T-1) ...
Beanfield No 1 HL, BEANFIELD #1 HL, Uppingham Road, CORBY Northamptonshire, NN17 2UJ (7 components)
• Auxiliary supply is subtracted prior to Bespoke Metering point MSID - NIA M1 ? 18042602
• The CMU Component reduces import demand by turning on back up generation.
Active • 2027-28 (T-4), 2020-21 (T-1) ...
Berry Agile Solutions, Ellough Industrial Area, Ellough, Suffolk, NR34 7TB, UK (4 components)
• Gas fired generating units
• The CMU Component reduces import demand by turning off equipment and other non-essential loads.
Active • 2024-25 (T-1), 2023-24 (T-4) ...
Berry, Corby BMS Sallow Road, Weldon Industrial Estate, Corby, Northamptonshire, NN17 5JX (5 components)
• The CMU Component reduces import demand by turning off equipment and other non-essential loads.
• Three POSGU (1.26MW, 1.0MW, 1.454MW) providing balancing services
Active • 2025-26 (T-4), 2024-25 (T-1) ...
Bond Avenue Bletchley Milton Keynes MK1 1JJ (19 components)
• Component has yet to be procured.
• The CMU component comprises of three 2MW Reciprocating Gas Engines
Active • 2028-29 (T-4), 2022-23 (T-4) ...
Bond Estates Milton Keynes MK1 1JJ (2 components)

The CMU component comprises of three 2MW Combined Cycle Gas Turbines (CCGT)

Inactive • 2017-18 (T-1)
Brackley STW, BRACKLEY STW (NEW), Turweston Field, BRACKLEY Northamptonshire, NN13 5JB, (6 components)

The CMU Component reduces import demand by turning on back up generation.

Inactive • 2020-21 (T-1), 2019-20 (T-1)
Cantelo Reception, UK Power Reserve Ltd, Bradon Farm, Isle Abbots, Taunton, Somerset. TA3 6RX (17 components)
• New build battery storage.
• The CMU is a electro-chemical Lithium-ion battery storage system connected to the transmission system at the National Grid Transmission Substation.
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
Active • 2027-28 (T-4), 2026-27 (T-4) ...
Carrington Power Station 132 Manchester Road Carrington Manchester M31 4AY United Kingdom (57 components)
• CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network
• The CMU component is a combined cycle gas turbine
• one CHP (1.9MW rating) in a horticulatural environment with no aux load
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Corby 3 - Sallow Road, Hunters Court, Corby, Northamptonshire, NN17 5JX (11 components)

The CMU Component reduces import demand by turning off equipment and other non-essential loads.

Active • 2024-25 (T-4), 2023-24 (T-1) ...
Cowley Substation Blackberry Lane Garsington Oxfordshire OX44 9BD (6 components)
• The CMU is a electro-chemical Lithium-ion battery storage system connected to the transmission system at the National Grid Transmission Substation.
• The CMU is a electro-chemical battery storage system connected to the transmission system at the National Grid Transmission Substation.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Cowley Substation Blackberry Lane Garsington Oxfordshire OX44 9BD (8 components)
• Combined Heat and Power Plant Grimsby made up of 5 generators totalling 30MW however the export capacity is limited to 6.MW (other generators are on site are defunct) so the participating generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.943 MW as per the 3 highest export peaks
• The CMU is a electro-chemical Lithium-ion battery storage system connected to the transmission system at the National Grid Transmission Substation.
• The CMU is a electro-chemical battery storage system connected to the transmission system at the National Grid Transmission Substation.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Croft Road, Coventry, CV1 3AZ (2 components)

"Planet Ice - UK Croft Road, Coventry, CV1 3AZ The CMU Component reduces import demand by turning off equipment and other non-essential loads."

Inactive • 2017-18 (TR)
DEANSHANGER HL, DEANSHANGER HL, DEANSHANGER, MILTON KEYNES, MK19 6BJ, (7 components)
• The CMU Component reduces import demand by turning on back up generation.
• Unproven DSR Component
Inactive • 2022-23 (T-4), 2020-21 (T-1) ...
Downing Street, Smethwick, West Midlands, B66 2PG (4 components)

"EMR European Metal Recycling Downing Street, Smethwick, West Midlands, B66 2PG The CMU Component reduces import demand by turning off equipment and other non-essential loads."

Inactive • 2017-18 (TR)
Drayton Manor Farm, Alcester Road, Stratford-Upon-Avon, CV37 9RG (7 components)
• 0.400MW of storage located at Drayton Manor Farm, Alcester Road, Stratford-Upon-Avon, CV37 9RG
• Battery storage located at Drayton Manor Farm, Alcester Road, Stratford-Upon-Avon, CV37 9RG with a nameplate capacity of 1.000 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU over 3 settlement periods identified over the previous months, per Capacity Market rules 3.5.3 & 3.5.4.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
DUSTON MILL-PITSFORD WA, DUSTON MILL RIVER INTAKE, NN5 6ER (19 components)

The CMU Component reduces import demand by turning off equipment and other non-essential loads.

Active • 2025-26 (T-4), 2024-25 (T-4) ...
2.81 MW
Eathorpe RI, Eathorpe, Leamington Spa, Warwickshire, CV33 9DE (6 components)

The CMU Component reduces import demand by turning off equipment and other non-essential loads.

Inactive • 2022-23 (T-1), 2021-22 (T-1)
Eathorpe RI, Eathorpe, Leamington Spa, Warwickshire, CV33 9DF (3 components)

The CMU Component reduces import demand by turning off equipment and other non-essential loads.

Inactive • 2023-24 (T-1)
2.81 MW
Loading map...
Showing 25 locations