3 unique locations - 3.4MW total capacity

Michelin Tyre Company Limited, Campbell Road, Stoke On Trent, Staffordshire, ST4 4EY (16 components)
• A gas engine CHP site providing hot water to an industrial unit
• CMU consisting of multiple reciprocating engines and alternators
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2027-28 (T-4), 2026-27 (T-4) ...
15.57 MW
New Galloway, Castle Douglas, Kirkcudbrightshire, DG7 3SF, Scotland (43 components)
• Glenlee hydro power station - Unit 1, part of the Galloway hydroelectric scheme. The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
• Glenlee hydro power station - Unit 1, part of the Galloway hydroelectric scheme. The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
• Glenlee hydro power station - Unit 2, part of the Galloway hydroelectric scheme The registered capacity of the Glenlee hydro power station is 30MVA or 24MW at 0.8PF and each of the 2 identical generating unit components at the station is 12MW.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
78.70 MW
Tees Valley Nursery, The Moat, Belasis Hall, TS23 4ED (34 components)
• District heating implementation with one asset 1.013MW exporting excess capacity to distribution network. Primary fuel type = Natural Gas. All generation unit capacities are nominal and allow for site-specific variations.
• The CMU component TEES01 is one gas-fired Jenbacher CHP engine. It will be supplying heat, CO2 and power to the on-site tomato Nursery all year.
• The CMU component TEES02 is one gas-fired Jenbacher CHP engine. It will be supplying heat, CO2 and power to the on-site tomato Nursery all year.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
25.22 MW