Capacity Market Search

Displaying items 31 - 40 of 49 matching components (Page 4 of 5)

Component Results (49)

Sort by: Relevance Location Date
Sorted by Relevance

DEBUG: Template sees CMU ID: S22G02 | DB ID: 23654

Sembcorp UK Headquarters Wilton International Middlesbrough TS90 8WS United Kingdom

CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S22G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.

Sembcorp Utilities (UK) Limited CMU: S22G02 Combined Heat and Power (CHP) Capacity N/A 2022-23 (T-4) Four Year Ahead Capacity Auction

DEBUG: Template sees CMU ID: S22G03 | DB ID: 23655

Sembcorp UK Headquarters, Wilton International, Middlesbrough, TS90 8WS

S22G03 will be a OCGT in CHP Configuration within the (former ICI) Wilton Site. CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1.

Sembcorp Utilities (UK) Limited CMU: S22G03 Combined Heat and Power (CHP) Capacity N/A 2022-23 (T-4) Four Year Ahead Capacity Auction

DEBUG: Template sees CMU ID: S22S11 | DB ID: 23656

Sembcorp UK Headquarters, Wilton International, Middlesbrough, TS90 8WS

(Please note: CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S22S11 is a Steam Turbine in CHP Configuration within the (former ICI) Wilton Site.

Sembcorp Utilities (UK) Limited CMU: S22S11 Combined Heat and Power (CHP) Capacity N/A 2022-23 (T-4) Four Year Ahead Capacity Auction

DEBUG: Template sees CMU ID: S21G01 | DB ID: 18287

Sembcorp UK Headquarters, Wilton International, Middlesbrough, TS90 8WS

(Please note: CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S21G01 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.

Sembcorp Utilities (UK) Limited CMU: S21G01 CHP and autogeneration Capacity N/A 2021-22 (T-4) Four Year Ahead Capacity Auction

DEBUG: Template sees CMU ID: S21G02 | DB ID: 18288

Sembcorp UK Headquarters Wilton International Middlesbrough TS90 8WS United Kingdom

CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S21G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.

Sembcorp Utilities (UK) Limited CMU: S21G02 CHP and autogeneration Capacity N/A 2021-22 (T-4) Four Year Ahead Capacity Auction

DEBUG: Template sees CMU ID: S21S11 | DB ID: 18289

Sembcorp UK Headquarters, Wilton International, Middlesbrough, TS90 8WS

(Please note: CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S21S11 is a Steam Turbine in CHP Configuration within the (former ICI) Wilton Site.

Sembcorp Utilities (UK) Limited CMU: S21S11 CHP and autogeneration Capacity N/A 2021-22 (T-4) Four Year Ahead Capacity Auction

DEBUG: Template sees CMU ID: S20G01 | DB ID: 15389

Sembcorp UK Headquarters, Wilton International, Middlesbrough, TS90 8WS

(Please note: CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S20G01 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.

Sembcorp Utilities (UK) Limited CMU: S20G01 Capacity N/A 2020-21 (T-4) Four Year Ahead Capacity Auction

DEBUG: Template sees CMU ID: S20G02 | DB ID: 15390

Sembcorp UK Headquarters Wilton International Middlesbrough TS90 8WS United Kingdom

CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S20G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.

Sembcorp Utilities (UK) Limited CMU: S20G02 Capacity N/A 2020-21 (T-4) Four Year Ahead Capacity Auction

DEBUG: Template sees CMU ID: S20S11 | DB ID: 15391

Sembcorp UK Headquarters, Wilton International, Middlesbrough, TS90 8WS

(Please note: CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S20S11 is a Steam Turbine in CHP Configuration within the (former ICI) Wilton Site.

Sembcorp Utilities (UK) Limited CMU: S20S11 Capacity N/A 2020-21 (T-4) Four Year Ahead Capacity Auction

DEBUG: Template sees CMU ID: S19GT2 | DB ID: 9126

Sembcorp UK Headquarters Wilton International Middlesbrough TS90 8WS United Kingdom

CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S19GT2 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.

Sembcorp Utilities (UK) Limited CMU: S19GT2 Combined Heat and Power (CHP) Capacity N/A 2019-20 (T-1) One Year Ahead Capacity Auction